Your Rational® ClearQuest® database
schema, which your project manager can customize, may support these common
change request management actions:
- Marking activities as duplicate
- Reopening closed activities
- Postponing activities
Your database schema may provide various ways to use these
actions. For example, record types that can be postponed may have a Postpone command
that you can choose after clicking Actions in the Record
form pane.
Keep the following concepts in mind concerning the UCM integration
with Rational ClearQuest while
using any schema-specific actions:
- Your project manager can set up each record type that is
enabled for UCM to behave differently; some actions may not be available for
all record types.
- You cannot move an activity to another development stream.
However, you can move versions in an activity change set to another activity
in the same stream or to an activity in a different stream.
- You
cannot delete an activity that is either currently set in a view or that contains
versions in its change set. The UCM View field in the ClearQuest Query results
pane indicates whether an activity is currently set. The activity Change
Set list, which is available from the ClearQuest Record
form pane or from an activity's properties sheet, displays an activity's change
set.
- It is risky to work in a development stream that contains
activities you do not intend to deliver. Keeping undelivered activities in
your development stream increases the risk that, after a rebase operation,
your development stream does not contain a cohesive set of versions. To avoid
this increased risk, if you begin working on an activity and then postpone
it until the next release, move the work to the new project and then create
and work in a new development stream.