The scope of the test effort is clearly identified
It must state the following:
-
Stages and types of test to be implemented and executed
-
Target-of-test features or functions to be tested / not tested (if appropriate)
-
Any assumptions, risks, or contingencies which may affect or impact the test effort
|
The artifacts used to generate the test plan are clearly identified
| Version information should be included. |
Each project requirement has at least one associated requirement for test or justification
If there is no associated test requirement, then a statement should be included that justifies why it is not a
requirement for test
|
All the requirements for test have been identified and prioritized
| Each of the different types of tests to be implemented and executed should be identified and prioritized. |
A clear and concise test strategy is documented for each type of test
For each test strategy, has the following information has been clearly stated:
-
The name of the test and its objective
-
A description of how the test will be implemented and executed
-
A description of the metrics, measurement methods, and criteria to be used evaluate the quality of the
target-of-test and completion of the test
|
All the resources needed have been identified
| This includes hardware, software, and personnel. |
Schedule or list of milestones identifies the major project and test related tasks
| Start and end dates, and / or effort should be included. |
The artifacts created by the test tasks are documented
| This includes identifying the artifacts, documenting when the artifacts are made available, how they will be distributed,