This plan defines an explicit approach for controlling changes, including defining states for the change request
artifact and tasks for transitioning the change request artifact between states. This plan is useful in a number
of situations, including:
-
When there is a group of stakeholders outside the project team that needs to approve and verify certain kinds of
changes
-
When a baselined work product is part of a contract in which changes need to be strictly controlled and approved
-
When changes need to be tightly controlled (such as late in an iteration or release cycle) for stabilization
purposes
|