You can remove and replace the power-cable assembly if you have problems with the power
supply and suspect that a power or signal cable is defective.
Before you begin
The power-cable assembly is composed of two power cables in a SAN Volume Controller 2145-CG8
or 2145-CF8 node and a signal cable that are bound together. You can remove the power-cable
assembly if you have problems with the power supply and suspect that a power or signal cable is
defective.
Make sure that power to the SAN Volume Controller 2145-CG8
or 2145-CF8 node is turned off before you remove the power-cable assembly. When removing the power-cable
assembly, ensure that you also remove it from the uninterruptible power
supply.
Turn off the node while ensuring that its data is mirrored and
synchronized, as described in MAP 5350: Powering off a node.
About this task
To remove the power-cable assembly, complete steps 1 through 7.
To replace the power-cable assembly, complete steps 8 through 12.
Procedure
Removing the power-cable assembly
- Check the SAN Volume Controller 2145-CG8
or 2145-CF8 node power LED
( 1 in Figure 1).
- If the light is on, go to step 2.
- If the light is either off or flashing, power has already been removed from the IBM Spectrum Virtualize™ node. Go to step 7.
Figure 1. Power LED on the 2145-CG8 or 2145-CF8
operator-information
panel
Important: Nodes operate in pairs. Both nodes are in the same I/O group. One node must
be operational if you are servicing the other node. If both nodes are not functioning, you cannot
access any of the disks in that I/O group.
- Turn off the node while ensuring that its data is
mirrored and synchronized.
See MAP 5350: Powering off a node for information.
Attention: If both IBM Spectrum Virtualize nodes
are online, removing the power from one IBM Spectrum Virtualize can
cause performance degradation while I/O operations are automatically
rerouted to other IBM Spectrum Virtualize.
Ensure that this performance outcome is acceptable before continuing
with this procedure.
- Press and release the power-control button
1 shown in Figure 1. Wait
one minute for the IBM Spectrum Virtualize to turn off.
Ignore a missing node error code if displayed by other nodes in the cluster. When maintenance
procedures are completed, the error will resolve itself.
- If necessary, pull back the cable-management
arm, remove any cable ties or hook-and-loop fasteners that might be
securing the power cords, and free the power cords from the cable-management
arm.
- Remove the cable-retention bracket. See Removing the cable-retention bracket for details.
- Remove the cable-retention bracket from the 2145
UPS-1U. See Removing and replacing the power cable-retention bracket: 2145 UPS-1U for details.
- Remove each power cord and serial cable from the back of the
node.
Replacing the power-cable assembly
- Replace each power cord and verify that each cord that you replace is seated well.
- Replace the serial cable for the node and
verify that each serial cable that you replace is seated well.
- Replace the cable-retention bracket and the 2145
UPS-1U cable-retention
bracket.
- If possible, route the power cords on the
cable-management arm, secure the power cords with cable ties or hook-and-loop
fasteners, and close the cable-management arm.
- If the node does not turn on automatically, press and release the power-control button.
Note: The 2145
UPS-1U
turns off only when its power button is pressed, input power has been lost for more than five
minutes, or the IBM Spectrum Virtualize node has shut it
down following a reported loss of input power.