Installing the support rails: 2145-CG8 or 2145-CF8
Install the support rails that hold the 2145-CG8 or 2145-CF8 in the rack.
Before you begin
Notes:
- With some types of racks, you might find it helpful to remove the rack doors and side panels to provide easier access during installation.
- The slide rails are marked (RIGHT / FRONT and LEFT / FRONT) for proper placement on the rack flanges.
- The front and back of each rail has a spring-loaded rail-locking carrier, which can be locked in the open position and then released when the rail is in the rack.
When you are ready to install the support rails, use the customer's hardware-location chart and the Electronic Industries Alliance (EIA) positions on the rack to determine where in the rack that the SAN Volume Controller node is to be installed.
About this task
To install the support rails, follow these steps:
Procedure
Results
The installation of the support rails for the 2145-CG8 or 2145-CF8 is complete.