Installing the SAN Volume Controller 2145-DH8
You must complete several tasks to install SAN Volume Controller 2145-DH8 node.
About this task
Installing a SAN Volume Controller 2145-DH8 node consists of the following tasks:
- Installing the support rails in the rack cabinet.
- Installing the node in the rack.
- Installing the cable-management arm in the rack cabinet.
Important: Do not connect the power to the node until the day that you will
be powering it on by pressing the power button. The batteries can become discharged if the node is
connected to power, but not powered on. To prevent this from happening, complete the appropriate
steps from Table 1.
| In this situation . . . | Complete the following steps |
|---|---|
| You connect the power to the node, but might not power it on by pressing the power button on the same day. |
|
| You power off the node, and might not power it on the same day. |
|
| You disconnect the power from the node, and might not reconnect power to it again on the same day. |
|