Before you remove the 2145 UPS-1U
,
read all safety notices.
Before you begin
Use the reference numbers in parentheses at the end of each notice (for example,
D005) to find the matching translated notice in IBM System Storage SAN Volume Controller Safety Notices.
DANGER
Uninterruptible power supply
(UPS) units contain specific hazardous materials. Observe the following precautions if your product
contains a UPS:
- The UPS contains lethal voltages. All repairs and service must be performed only by an
authorized service support representative. There are no user serviceable parts inside the UPS.
- The UPS contains its own energy source (batteries). The output receptacles might carry live
voltage even when the UPS is not connected to an AC supply.
- Do not remove or unplug the input cord when the UPS is turned on. This removes the safety ground
from the UPS and the equipment connected to the UPS.
- The UPS is heavy because of the electronics and batteries that are required. To avoid injury,
observe the following precautions:
- Do not attempt to lift the UPS by yourself. Ask another service representative for
assistance.
- Remove the battery, electronics assembly, or both from the UPS before removing the UPS from the
shipping carton or installing or removing the UPS in the rack. (D007)
CAUTION:
This part or unit is heavy but has a weight smaller than 18 kg (39.7
lb). Use care when lifting, removing, or installing this part or unit. (C008)
About this task
Perform the following steps to remove the 2145 UPS-1U
.
Attention: Check to make sure that the
SAN Volume Controller
that
is powered by this
2145 UPS-1U
is
shut down and turned off, prior to step 1. See
MAP 5350: Powering off a node.
Procedure
- At the front of the 2145 UPS-1U
,
press and hold the on/off button ( 1 in Figure 1) until the power light is extinguished (approximately 5
seconds). On some versions of the 2145 UPS-1U
, you need a pointed device, such
as a screwdriver, to press the on/off button. The 2145 UPS-1U
enters standby mode.
Figure 1. The 2145 UPS-1U
front-panel assembly
- At the back of the 2145 UPS-1U
,
remove the power cable retainer before disconnecting the SAN Volume Controller
power
cable from load segment receptacle 2 ( 3 in Figure 2).
- Disconnect the signal cable from the communication port
( 2 in Figure 2).
- Disconnect the main power cable from the main power source
( 1 in Figure 2).
Figure 2. 2145 UPS-1U
(rear
view)
Some SAN Volume Controller
node types have two power
supply units. Both power supplies must be connected to the same 2145 UPS-1U
. The SAN Volume Controller 2145-CF8 is an example of a node that has
two power supplies.
- Remove the 2145 UPS-1U
front
panel, as shown in Figure 3.
Note: If you are having difficulty pulling the right
side of the panel free from the 2145 UPS-1U
,
insert a flat-blade screwdriver between the right side of the cover
and the frame and gently pry it free.
Figure 3. Removing the 2145 UPS-1U
front panel
- Disconnect the internal battery connector, which is circled
in Figure 4.
Figure 4. The 2145 UPS-1U
internal-battery connector
- After pulling the two connectors apart, cover the exposed
battery connector (shown in Figure 5)
with adhesive tape.
Figure 5. The 2145 UPS-1U
internal
battery connector with protective tape
- Reinstall the front panel.
- At the front of the 2145 UPS-1U
,
unscrew the two mounting screws 1 , as shown in Figure 6.
Figure 6. Mounting screws for the 2145 UPS-1U
- From the back of the rack, push the 2145 UPS-1U
forward
approximately 5 cm (2 in) to enable you to pull it from the rack.
- Go to the front of the rack.
- Pull the 2145 UPS-1U
forward
and remove it from the rack.