Verifying the SAN Volume Controller 2145-DH8 installation

You must verify the installation after the installation has completed.

Before you begin

This task shows you how to verify the installation after you install the system in the rack and connect it to the storage area network (SAN) and the Ethernet.

Note: If at any point the system does not operate as described, see MAP 5000: Start, unless a different maintenance analysis procedure (MAP) is specified.

Procedure

To verify the installation, complete the following steps.

  1. Press the power-control button. Because the button is recessed, you might need a pointed device, such as a screwdriver, to press the power-control button. Verify that the green power LED is lit. If the LED is not illuminated, see MAP 5000: Start to repair the problem.
    Note: You do not need to install any software. The node boots automatically.

    The system runs an extended series of power-on self-tests. The node might appear to be idle for up to 5 minutes after powering on the system.

    Figure 1 shows the controls and indicators on the front panel that verify the installation. Figure 2 is a close-up view of the operator-information panel.

    Figure 1. SAN Volume Controller 2145-DH8 front panel
    This figure shows the front panel of the SAN Volume Controller 2145-DH8
    •  1  Hard disk drive activity LED (green)
    •  2  Hard disk drive status LED (amber)
    •  3  USB port
    •  4  Video connector
    •  5  Operator-information panel
    •  6  Rack release latch
    •  7  Node status LED
    •  8  Node fault LED
    •  9  Battery status LED
    •  10  Battery fault LED
    •  11  Batteries
    •  12  Hard disk drives
    Figure 2. SAN Volume Controller 2145-DH8 operator-information panel
    Operator information panel
    •  1  Power-control button and power-on LED
    •  2  Ethernet icon
    •  3  System-locator button and LED (blue)
    •  4  Release latch for the light path diagnostics panel
    •  5  Ethernet activity LEDs
    •  6  Check log LED
    •  7  System-error LED (amber)
  2. Verify that the node boots without error. When the battery charge is low, the battery status LED flashes.

Results

The installation of the system hardware is now complete. No software installation is required.