Installing
To install your system, you must deploy and configure the server hardware.
- Installation guidelines
Before you install the support rails, review and follow the installation guidelines. - Installing the SAN Volume Controller 2145-SV1 node
There are several steps that you must complete to prepare for and then install the SAN Volume Controller 2145-SV1 hardware. - Installing the SAN Volume Controller 2145-DH8 node
There are several steps that you must do to prepare for, and then install the SAN Volume Controller 2145-DH8 hardware. - Installing the 2145-92F expansion enclosure
Before you install the 2145-92F expansion enclosure, review the following guidelines. - Installing support rails for 2U SAS expansion enclosures
Before you install 2U SAS expansion enclosures, you must first install support rails. - Installing the optional 2U SAS expansion enclosure into the rack
The 2145-12F or 2145-24F SAS expansion enclosures can be installed in a separate rack or in the same rack as the system nodes. - Connecting the optional 2U SAS expansion enclosures to the 2145-SV1
After you install the 2145-24F or 2145-12F SAS expansion enclosures into the rack, you must connect them to each 2145-SV1 node in the IO group that will use them. - Connecting the optional 2U SAS expansion enclosures to the 2145-DH8
After you install the 2145-24F or 2145-12F SAS expansion enclosures into the rack, you must connect them to each 2145-DH8 node in the IO group that will use them.