Physical installation planning

Before you set up your system environment, you must verify that the prerequisite conditions for the system are met.

About this task

This information applies to the supported hardware components. Answer the following questions before you start the installation process.

  1. Does your physical site meet the environment requirements for your system?
  2. Do you have adequate rack space for your hardware? Ensure that you have the following rack space for your components:
    • The SAN Volume Controller 2145-DH8 : Two EIA units high.
  3. Do the power circuits that you are planning to use have sufficient capacity and the correct sockets for your installation?
    • A clearly visible and accessible emergency power off switch is required.
  4. Have you provided appropriate connectivity by preparing your environment?
  5. Do you have a keyboard and display available in the unusual event that a service action requires them?