After you install all hardware components, you must power on the system and check its
status.
About this task
Attention: Do not power on the system with any open bays or slots. Open bays or slots
disrupt the internal air flow, causing the drives to receive insufficient cooling.
Every unused drive bay must be occupied by a filler panel.
Filler panels must be installed in all empty host interface adapter slots.
Note: Each power supply unit includes a cable retainer to
secure the power cable.
Use the cable retainers to secure the power cables from being accidentally
pulled out of the enclosure. The cable retainer, which is on the back of each PSU, has a curved
opening that faces the rear of the PSU. After you plug the power cables in to the PSU, slip the
power cable behind the retainer. Then, pull the cable back into the retainer opening to secure the
cable.
Each cable must be routed through the retainer, as shown in Figure 1. For PSU 1, hook the power cable underneath
the cable retainer so the cable can extend to the left. For PSU 2, make a loop to secure the cable
under the retainer and extend the power cable to the right side of the enclosure. Figure 1. Routing the power cables through the cable retainers
To remove the power cable, push the cable forward to unhook it from the cable retainer. Then,
unplug the cable from the PSU.
Procedure
To power on the system, complete the following steps.
Wait for all expansion enclosures to finish powering on.
Power on the control enclosure. Use the supplied power cords to connect both power supply units
of the enclosure to their power sources.
If the power sources have circuit breakers or switches, ensure that they are turned on. The
enclosure does not have power switches.
Notes:
Each enclosure has two power supply units. To provide power failure redundancy, connect the two
power cords to separate power circuits.
Ensure that each power cable is secured to each PSU on the back of the enclosure.
From the rear of the control enclosure, check the LEDs on each node canister (see Figure 2).
Figure 2. Node canister LEDs
1 Power
2 Status
3 Fault
The canister is ready for initialization with no critical errors when Power is
illuminated, Status is flashing, and Fault is off.
What to do next
Next, you connect an Ethernet cable to the technician port on the control enclosure, and
initialize the system.