You can use the command-line interface (CLI) to install software updates.
Before you begin
Follow these steps to update to version 8.1.0 or later from version
7.7.0 or later.
Note: If you are updating from version 8.3.0.0 or earlier to
any version before 8.3.1.2, configuring IP by using the cfgportip command with
gateway 0.0.0.0 is not supported. If you already have any configured IP using
cfgportip with gateway as 0.0.0.0, then either change the gateway address or
update directly to 8.3.1.2 or later.
You can use the
command-line interface to resolve multipathing issues when nodes go offline for updates. You can add
the ability to override the default 30 minute mid-point delay, pause an update, and resume a stalled
update by following these steps:
- To start an update but pause at the halfway point, enter the following command:
applysoftware -file filename -pause
- To start an update but then pause before you take the node offline for an update, enter the
following
command:
applysoftware -file filename -pause -all
- To resume a stalled update and pause at the halfway point, enter the following
command:
applysoftware -resume -pause
- To resume a stalled update and pause before you take the remaining nodes offline for an update,
enter the following command:
applysoftware -resume -pause -all
Note: The
-all parameter enables the update to pause indefinitely before each node goes
offline for an update. This pause happens before the existing object-dependent volume check is
carried out. The -resume parameter enables the user to continue the
update.
Important: If you update your
system software to version 8.1.1 or later from a version earlier than 8.1.0, on a system where
you have already installed more than 64 GB of RAM, all nodes return from the update with an
error code of 841. Versions 8.1.0 and later allocate memory in a different way than previous
versions, so the RAM must be "accepted" again. To resolve the error, complete the following steps:
- On a single node, run the svctask
chnodecanisterhw command. Do not run the command on more than one node at a
time.
- Wait for the node to restart and return without the error.
- Wait an additional 30 minutes for multipath drives to recover on the host.
- Repeat this process for each node individually until you clear the error on all nodes.
About this task
To update the system, follow these steps:
Procedure
-
You must download, install, and run the latest version of the test utility to verify that no
issues exist with the current system.
Important: After you install and run the test utility by using either the
management GUI or the CLI, you must return to step
2 on this page.
You can download and install the most current version of this tool at the following website. The
link provides instructions for using either the management GUI or the CLI to install and run the
test utility.
http://www.ibm.com/support/docview.wss?uid=ssg1S4000585
-
Download the latest code from the www.ibm.com/support site.
- If you want to write the code to a CD, you must download the CD image.
- If you do not want to write the code to a CD, you must download the installation
image.
-
Use PuTTY scp (pscp) to copy the update files to the node.
-
Ensure that the update file was successfully copied.
Before you begin the update, you must be aware of the following situations:
- The installation process fails under the following conditions:
- If the code that is installed on the remote system is not compatible with the
new code or if an intersystem communication error does not allow the system to check that the code
is compatible.
- If any node in the system has a hardware type that is not supported by the new code.
- If the system determines that one or more volumes in the system would
be
taken offline by
rebooting the nodes as part of the update process. You can find details about
which volumes would be affected by using the lsdependentvdisks command. If you
are prepared to lose access to data during the update, you can use the force flag to override this
restriction.
- The update is distributed to all the nodes in the system by using internal
connections between the nodes.
- Nodes are updated one at a time.
- Nodes run the new code concurrently with normal system activity.
- While the node is updated, it does not participate in I/O activity in the I/O
group. As a result, all I/O activity for the volumes in the I/O group is directed to the other node
in the I/O group by the host multipathing software.
- There is a thirty-minute delay between node updates. The delay allows time for
the host multipathing software to rediscover paths to the nodes that are updated. There is no loss
of access when another node in the I/O group is updated.
- The update is not committed until all nodes in the system are successfully
updated to the new code level. If all nodes are successfully restarted with the new code level, the
new level is committed. When the new level is committed, the system vital product data (VPD) is
updated to reflect the new code level.
- Wait until all member nodes are updated
and the update is committed before you invoke the new functions of the updated code.
- Because the update process takes some time, the installation command completes as soon as the
code level is verified by the system. To determine when the update is completed, you must either
display the code level in the system VPD or look for the Software update
complete event in the error/event log. If any node fails to restart with the new code
level or fails at any other time during the process, the code level is backed off.
- During an update, the version number of each node is updated when the code is installed and the
node is restarted. The system code version number is updated when the new code level is
committed.
- When the update starts, an entry is made in the error or event log and another entry is made
when the update completes or fails.
-
Issue this CLI command to start the update process:
applysoftware -file software_update_file
Where
software_update_file is the name of the code update file in the
directory you copied the file to in step
3.If the system identifies any volumes that would go offline as a result of rebooting
the nodes as part of the system update, the code update does not start. An optional
force parameter can be used to indicate that the update continues regardless of
the problem identified. If you use the
force parameter, you are prompted to
confirm that you want to continue.
The
behavior of the force parameter changes, and it is no longer required when you
apply an update to a system with errors in the event log.
-
If you are updating from a release before version 7.4.0, issue the
following CLI command to check the status of the code update process:
svcinfo lssoftwareupgradestatus
This command displays
inactive when the update is complete.
Note: If a
status of stalled_non_redundant is displayed, proceeding with the
remaining set of node updates might result in offline volumes. Contact a service representative to
complete the update.
-
If you are updating from version 7.4.0 or later, issue the
following CLI command to check the status of the code update process:
lsupdate
This command displays
success when
the update is complete.
Note: If a status of stalled_non_redundant is displayed,
proceeding with the remaining set of node updates might result in offline volumes. Contact a service
representative to complete the update.
-
If you updated from a release before version 7.4.0, you receive the status message
system_completion_required.
To complete the update process, issue the command applysoftware -complete. After
that command is run, you can run lsupdate to see the progress of the update
completion.
-
To verify that the update successfully completes, issue the
lsnodecanistervpd CLI command for each node that is in the system.
The code version field displays the new code level.
Results
When a new code level is
applied, it is automatically installed on all the nodes that are in the
system.Note: An automatic system update can take up to 30 minutes per
node.